A brief analysis of the transformation process of coating production line
Time:2012-10-22 11:51:38

       The painting production line of the complete machine is designed by the former First Design and Research Institute of machinery Industry, which adopts the advanced and mature industrial art in China at that time, and improves the mechanization and automation level of the painting production line, so as to improve the working environment and reduce the labor intensity of workers. At the same time, it has earnestly implemented the relevant state laws and regulations, norms and standards, and worked hard to do a good job in environmental protection and occupational safety and health.


       The whole production line by line, drying, screening, drying, paint on the surface and, offline 7 station such as composition, except on and off the five stations by an organic water drying room, shielding room, water spray paint room, flow flat room and dry room of a closed production line, and workshop is separated, ensures the whole paint areas relatively clean. In addition, a complete machine cleaning section is built at one end of the workshop for secondary cleaning of the complete machine. The whole machine adopts double board ground chain transportation to improve the mechanization level.


       Process flow: water gun oil removal cleaning -- on line -- hot air drying -- shielding -- surface paint spraying -- leveling -- drying -- removing shielding -- off line.


       The operation time of each station is 45min, and the cycle time of the pipeline can be adjusted appropriately according to the actual use.


       The paint varieties are komatsu yellow acrylic polyurethane enamel and the spray gun is electrostatic mixed air spray gun.


       The coating production line can produce 2000 loaders per year when only units are arranged for production. The total number of designers in the coating workshop is 24, including 16 production workers. The average annual output of each production worker is 142 loaders.


Second, the question raises

       After 2003, due to the country to increase the investment in infrastructure, the loader industry into the good situation of flourishing production and marketing, several major loader production enterprises have reached their maximum output record. At the same time, each manufacturer has improved the appearance quality. The paint is mainly used to color the loader. The loader's appearance color is divided into two parts, which changes the loader's single color for a long time.


       With the increase of loader output and the extensive use of exterior paint color registration, several problems occurred in the application process of complete machine coating line:

       (1) the surface spray paint tinted homework makes loader shorter time () down on a painting area, and screen instead of to shorten the time, and extension of trend, make the whole assembly line beat changed, when in low yield, but increased the waiting time for some station, yield increase and then need to be partially blocked work offline.

       (2) Due to the shortened beat of the entire production line, there is a heating process in the water mark drying room, so that the temperature just rises to the specified temperature and sometimes even does not rise to the specified temperature, it needs to be transferred to the next station, which cannot play a role at all. However, the water mark drying room is a pass-through type, and the temperature immediately drops to the ambient temperature after the door is opened.

       (3) The drying room also has the same problem as the water mark drying room, which cannot give full play to the drying role.

       (4) The door of each chamber adopts pneumatic door, the time of switch is long, fully open or completely close is about 3-5min, in the whole beat is long (45min), do not feel, after the beat is shortened it seems a little too long.

       (5) the utilization rate of the waste gas treatment device is too low, because the exhaust gas in the paint room is fully mixed with water, and the air volume is large, so the organic solvent content discharged into the atmosphere can meet the emission standards. The drying chamber USES the hot air circulation, a small part of the exhaust gas emissions, this small part of the exhaust gas may exceed the standard, so most of the production lines have added activated carbon adsorption device.


3. Suggestions for improvement

       It is impossible to solve the above problems by using the current intermittent pass-through production line. To completely solve the above problem, only fundamentally change the production line type, or like a car factory adopted by type production line, continuous operation, every room body is longer, the whole production line without door, drying room a preliminary drying and strong cold area, and use the wind curtain interception heat, or use the Chambers and decorate, a spray room with 2-3 drying room, loader into the drying chamber immediately after spray paint, flat, drying in the process of heating up, some large-scale passenger car manufacturer both in this way.


Iv. Practical operation

With the increasing production of loaders, the measures taken by our company are as follows:

       1) After cleaning and removing oil, the loader should take the way of natural cooling and drying, pay attention to maintain balanced production, if the weather is bad, use the night time to dry.

       (2) When the production line is in operation, the water-mark drying room does not work, and most of the shielding work is carried out offline.

       (3) All the doors of the room are closed when painting, in order to save time. In this way, it is easy to cause the paint mist to fly to the shielding room and leveling room next to the paint room.

       (4) A new 720m2 hangar will be built for parking the loader sprayed with paint, and the painting and decoration work will be carried out here; When the temperature is low, use the evening time to dry.

       (5) Make some baffles of shield glass with tin sheet to save the time of shield glass.

    

       Through the above measures, the company has ensured the painting workshop in the case of no night shift, Nissan 15-20 loaders. Of course, the above measures are a little harmful to the production line. In order to improve the problem of drying in winter, the company plans to build a new drying room for drying the paint of the whole machine, and prepare to move the water-mark drying room below the line to play its role.

Service hotline

020-36860788

WeChat

Feedback

Feedback

主站蜘蛛池模板: 欧美黑人精品一区二区不卡 | 国产天美传媒性色av | 亚洲鲁鲁 | 国产福利视频在线精品 | 久亚洲一线产区二线产区三线产区 | 精品久久中文字幕97 | 日本欧美一区二区三区高清 | 黄色录像a级片 | 内射老阿姨1区2区3区4区 | 久久无码精品一区二区三区 | 国产精美视频 | 无码国产色欲xxxx视频 | 性生交大片免费中文 | 丰满人妻熟妇乱偷人无码 | 性xxxx视频播放免费 | 欧美另类又黄又爽的a片 | 国产v亚洲v欧美v精品综合 | 一本色道久久综合亚洲精品小说 | 日韩三级在线免费观看 | 久久99热只有频精品8 | 国产欧美日韩在线播放 | 成人午夜免费无码区 | 国产模特av私拍大尺度 | 成人网一区 | 欧美va免费高清在线观看 | 西西人体www大胆高清视频 | 欧美40老熟妇色xxxxx | 黄色免费观看高清 | 精品久久久久久亚洲 | 91麻豆网 | 欧美成人aa久久狼窝五月丁香 | 欧美 偷窥 清纯 综合图区 | 99婷婷| 2019久久久高清日本道 | 亚洲精品视频久久久 | 激情综合在线 | 无码av动漫精品一区二区免费 | 国产在线观看www污污污 | 亚洲中文久久精品无码照片 | 欧美一级淫片免费视频黄 | www.com黄色 | 成人深夜视频 | 日本亲与子乱人妻hd | 夜夜操网址 | 最新国产av最新国产在钱 | 少妇被粗大猛进进出出 | 午夜h| 制服丝袜人妻有码无码中文字幕 | 亚洲精品第一国产综合境外资源 | 久月婷婷 | 快播日韩 | 天堂…在线最新版资源 | 久久99精品福利久久久久久 | 日本一级黄色大片 | 国产亚洲一卡2卡3卡4卡网站 | 久久综合精品国产丝袜长腿 | 高清无码午夜福利在线观看 | 久久久久国色av免费看图片 | 免费污片在线观看 | 精品日本一区二区三区 | 亚洲综合小说另类图片五月天 | 日韩人妻少妇一区二区三区 | 国内精品伊人久久久久7777 | 亚洲七七久久桃花影院 | 有码在线 | 亚洲欧美在线观看 | 免费在线观看av网址 | 亚洲国产成人精品无码区软件 | 亚洲日本乱码一区二区在线二产线 | 不卡一卡二卡三乱码免费网站 | 国内精品免费久久久久软件 | 好紧好湿好爽免费视频 | 黄色av国产 | 手机看片欧美 | 中文字幕黄色av | 亚洲乱码中文字幕小综合 | 亚洲精品卡2卡三卡4卡2卡乱码 | 亚洲国产成人久久精品99 | 亚洲一区二区三区中文字幕 | 免费毛片视频网站 | 亚洲欧美另类在线图片区 | 国产欧美中文字幕 | 国产日韩欧美亚洲精品中字 | 欧美性生 活18~19 | 国产又色又爽又高潮免费 | 99在线精品视频 | 国产精选视频在线观看 | 邻居少妇张开腿让我爽了在线观看 | 国产乱码字幕精品高清av | 神马午夜视频 | 亚洲 日韩 国产 中文有码 | 中文字幕精品一二三四五六七八 | 国产成人精品日本亚洲专区61 | 欧美日韩偷拍视频 | 麻豆精品国产 | 男女啪啪永久免费观看网站 | 亚洲人人爽 | 一区二区观看 | 啪啪福利 |